How to make ERP Project Estimate
ERP Project Estimation Guidelines, Oracle Project Estimation Techniques, ERP software project estimation, creating a detailed work plan, develop the project scope, suggested approach, and preliminary budget.
The preliminary ERP application implementation project estimate is based on:
- What is the business objective?
- What is the scope of the project and how does it relate to the overall objective?
- Who will participate in the project (employees, consultants, or vendors)?
- What are the constraints affecting the project (timing, budget limitations, or organization changes)?
- Which applications will be implemented?
- Which sites will be involved?
- Will a phased-deployment be employed? If so, in what sequence will the applications be implemented?
- When will work commence?
- What experience does the organization have regarding the technology that will be used?
Before creating a detailed work plan, develop the project scope, suggested approach, and preliminary budget. The indicative Phase schedules needs to be derived in the respective phases during the ERP Implementation life-cycle based on the assumption of an average complexity of implementation, which includes the following assumptions:
- Industry Standard Processes
- Two to three Set of Books, 5/6 segment COA structure and single calendar
- No MRC or GCS requirements
- Simple Multi-Org structure with one Business Group, 2/3 LE, 2/3 OU and corresponding Inventory Orgs
- No Localization requirements
- Single geographical entity
- Not a Material Intensive Business
- Around 1000 Vendors and Customers
- Moderate Volumes of Transactions (~ 500 Invoices per Month)
- Dedicated Business Process Owners Time